Connection to the Bureau
Plan of connection to the FCBU's system
| ¹ |
Description |
Responsible part |
Approximate period |
1
.jpg)
|
Signing the agreement.
|
Bank,
FCBU
|
1-2 days |
| 2

|
Defining the project leader and contact persons responsible for organizational issues in work with the FCBU.
|
Bank
|
3 days
|
|
3

|
Transferring FCBU’s technical documentation to the bank.
|
Bank
|
2 days |
|
4
.jpg)
|
Making out the scheme of work with the Bureau.
|
Bank
|
5 days |
|
5

|
Designing the automatic transferring system.
|
Bank
|
15-40 days |
|
6

|
Testing the automatic transferring system.
|
Bank,
FCBU
|
5-15 days |
|
7

|
Training people, who are responsible for the work with the FCBU.
|
FCBU
|
1-2 days |
|
8
.jpg)
|
Start of work with the Bureau.
|
|
31-68 days from signint the agreement
|